Posted 21/6/08
Victoria's Planning Framework for Land Use and Development
1 EXECUTIVE SUMMARY
1.1 Introduction
The Victorian planning system provides the legislative and administrative
framework that regulates and manages the use and development of land in the state.
The Planning and Environment Act 1987 (the Act) outlines a number of planning
objectives such as the fair, orderly, economic and sustainable use and development
of land.
Planning schemes and planning permits are the major legislative
mechanisms for controlling land use and development. Planning schemes are statutory
documents that set out objectives, policies and provisions for the use and development
of land in the area to which they apply (usually a municipality). Where a planning
scheme requires it, a planning permit must be obtained to use or develop land for
certain purposes. The Act and Regulations establish the timeframes and procedures
to be followed in processing planning permit applications and amending planning
schemes.
Under the Act, a planning authority is responsible for
developing and amending a planning scheme, and for giving direction on how broader
state planning policies will be implemented in the local context. A responsible
authority administers the local planning scheme by processing and enforcing
planning permits, and in achieving consistency with the planning scheme. These roles
are performed by local councils in most cases.
The Minister for Planning has overall responsibility for the state’s
planning legislation and framework, and is both a planning and responsible authority
for a number of designated areas throughout Victoria. The minister also authorises
and approves amendments to planning schemes and reviews proposed developments that
have state-wide policy implications.
The Department of Planning and Community Development (DPCD) manages
the regulatory framework for land use planning, environment assessment and subdivisions
of land. It also provides advice on planning policy, information on land use and
development and administrative support to the minister.
Councils manage the day-to-day administration of local planning
schemes through processing applications for planning permits and ensuring consistency
with planning schemes. They also develop planning schemes and amend them as needed
to reflect changes to policy or local circumstances. State-wide, there were around
49 600 planning permit applications lodged in 2006–07.
Victoria’s planning system has been subject to continuous reform
since the early 1990s. As part of these reforms, the Act was amended in 1996 to
introduce the Victoria Planning Provisions (VPP) and establish new format planning
schemes with a strategic and performance-driven focus to reduce administrative costs
and increase efficiency of the planning system.
The VPP is a state-wide reference and statutory device used to
construct planning schemes. It ensures that consistent provisions for controlling
land use and development are maintained across Victoria, and that the structure
and format of all planning schemes is the same. The Ministerial Direction on the
Form and Content of Planning Schemes [1] requires that a planning scheme must include
the following parts of the VPP:
- the State Planning Policy Framework, which details the
state’s policies for key land use and development activities
- the Local Planning Policy Framework consisting of a Municipal
Strategic Statement and Local Planning Policies, which establish the local strategic
policy context for a municipality and how broader state policies will be achieved
in the local context
- key zones, overlays and other provisions that are relevant
to giving effect to state and local policy frameworks chosen as needed from
the VPP.
Following the introduction of the VPP, the new format planning
schemes were progressively implemented across the state and were largely in place
by 2000. The latest reforms (Better Decisions Faster 2002–05 and Cutting
red tape in planning 2006) have focused on opportunities to further improve
the effectiveness and efficiency of planning processes. In early 2007 an expert
working group was established in response to Action 10.2 of the Cutting red
tape in planning report. The working group’s Making local policy stronger
report included five recommendations that have been accepted by the government.
The February 2008 Annual Statement of Government Intentions
foreshadowed the review of the Planning and Environment Act 1987. It is
anticipated the new Act will be presented to Parliament in 2009.
The objective of this audit was to assess the effectiveness, economy
and efficiency of Victoria’s planning framework for land use and development at
the whole-of-state and local levels.
The audit examined whether:
- at the whole-of-state level:
- the key elements of planning schemes are clear and assist
robust and consistent decision-making
- adequate arrangements are in place to measure and report
the performance of the state’s planning framework.
- at the local council level:
- the requisite policies and procedures are in place, including
adequate quality-assurance arrangements to align council-level decisions with
the Planning and Environment Act 1987, the State Planning Policy Framework and
their own planning schemes
- the processing of planning permit applications and planning
scheme amendments complies with the Act and with their own planning schemes.
The audit examined the policies, procedures and activities of DPCD,
Maribyrnong City Council, City of Boroondara, City of Casey, City of Greater Shepparton,
Bass Coast Shire Council and Pyrenees Shire Council.
The audit scope did not extend to assessing the adequacy of specific
planning decisions or the related activities of the Victorian Civil and Administrative
Tribunal.
While the results at the local government level relate
directly to the councils we examined, the issues revealed are considered indicative
of practices in other councils. In this context, the associated findings should
be considered by all councils administering planning functions.
1.2 Findings
In line with the objectives of the audit, the findings are outlined
below in terms of the:
- clarity and robustness of key elements of planning schemes
- adequacy of performance measurement and reporting arrangements
- level of council compliance with the Act and planning schemes,
and adequacy of associated quality assurance arrangements.
1.2.1 Clarity and robustness of planning schemes
The major findings from the audit’s examination of planning schemes
were:
- The intended purpose and relationships between the key
VPP components of planning schemes are transparent, logical and consistent with
the objectives of the planning framework established under the Act.
- The underlying architecture of the VPP framework is sound,
however, a number of challenges and issues associated with its implementation
have emerged which are impeding the effective and efficient operation of planning
schemes.
- Some elements of the new format planning schemes have become
overly complex, are unclear and are not adequately achieving their original
intent as established under the VPP (as identified by a ministerial working
group) and need to be addressed.
- A series of actions designed to address these challenges
and improve the operation of planning schemes have recently been established.
1.2.2 Adequacy of performance measurement and reporting
The major findings from audit’s assessment of the adequacy of arrangements
in place for measuring and reporting on the performance of the state’s planning
system were:
- Existing arrangements within DPCD do not allow for comprehensive
measurement and monitoring of the overall performance of the planning system.
- DPCD should further develop these arrangements supported
by a structured program of stakeholder engagement.
- Performance measurement arrangements have not been developed
to assess the impact of changes to the legislative and regulatory framework
designed to improve the effectiveness and efficiency of statutory processes.
Consequently, it is unclear whether these changes have achieved their intended
goals.
- DPCD has facilitated a number of targeted reviews of the
VPP to improve their operation and achieve better planning outcomes in response
both to wider government policy developments and to issues raised by stakeholders.
However, these reviews have not been undertaken as part of an ongoing program
of continuous review.
- DPCD has developed products, such as codes of practice, to
assist councils in discharging their statutory obligations. Our assessment of
a selection of these products is that they are of a high standard. However,
based on our audit of councils, these products are under-promoted and underutilised.
- There are no performance standards in place for DPCD regions
to measure the effectiveness and efficiency of advisory and statutory support
services primarily provided to councils.
- Timeliness targets for the authorisation and assessment of
planning scheme amendments are in place, however, the calculation of actual
performance against the targets does not measure the total elapsed time to make
a decision.
1.2.3 Compliance with the Act and planning schemes and adequacy
of quality assurance
The major findings from the audit of selected councils in relation
to the planning scheme amendments were:
- Amendments are often complex but the time taken to complete
individual steps in the amendment process was excessive in some cases. The average
time from initiation to publishing a notice of approval of the amendment in
the Victorian Government Gazette across councils was nearly 22 months.
- Councils generally complied with the Act in considering amendment
requests.
- Reports to councils should be more rigorous and transparent
in terms of the justification for the amendment at the early consideration stage.
- Councils generally complied with the Act in relation to the
administration of notification procedures for parties considered to be materially
affected by the amendment. However, the basis upon which councils decided to
notify these parties was neither transparent nor adequately documented.
- Assessments following exhibition of an amendment and decisions
made by councils on how to proceed (i.e. adopt, modify or abandon an amendment)
were sound in most cases. Council officer reports, however, did not include
a thorough analysis of issues to assist consideration by councillors of the
appropriate course of action to be taken.
- Councils generally complied with the Act in their use and
administration of panel processes although some councils need to pay greater
attention to meeting the 28-day statutory timeframe for the public release of
panel reports.
- Councils complied with the Act in the adoption and submission
of amendments to the minister in the vast majority of cases. However, poor file
management in some councils meant they were unable to demonstrate whether there
was full compliance in all cases.
- Fee collection was satisfactory in most cases however,
some councils failed to record or collect all fees.
The major findings arising from the audit of selected councils
in relation to planning permit applications were:
- The average statutory time taken to process applications
across councils was 58 days and within the prescribed timeframe of 60 days.
- The total elapsed time to process applications, which is
affected by events not required to be accounted for in the prescribed timeframe,
was significantly higher in most cases (86 days on average). There is scope
for councils to improve the efficiency of the process by developing strategies
to reduce the time taken to manage events within the control of councils.
- Details of pre-application meetings were not systematically
recorded. Consequently, it was difficult to determine the extent to which these
meetings had occurred and whether they were effective in minimising delays.
- Councils did not adequately comply with the Act when amendments
were made to applications before a council decision. In most cases, a new application
form was not requested, the prescribed time to process the application was not
restarted and the need to notify and refer the application to affected parties
was not re-assessed.
- Most councils complied with the Act and the planning scheme
in giving notice of an application where it was considered that there was material
detriment to parties affected by the application. However, the rationale for
decisions concerning detriment was neither transparent nor adequately documented
in most cases.
- Councils appropriately forwarded applications to referral
authorities, and conditions requested by these authorities were applied to permits
by councils in accordance with the Act. However councils breached the Act by
failing to send copies of decisions to referral authorities in most cases.
- In four of the six councils examined, the assessments did
not give sufficient consideration to the Act or planning scheme. In 78 per cent
of cases examined, officer reports did not give adequate consideration to matters
specified in the Act, planning scheme or both.
- Considerable improvement in the quality assurance provided
by senior council planning staff over the accuracy and processing of permit
applications is required.
These findings require remedial action both at a local council
level and, due to their extent and significance, at the state-wide level via a multi-pronged
system-wide approach coordinated by DPCD in partnership with local government and
key stakeholder groups. This approach should adopt the specific goal of raising
the standard of statutory planning in councils and therefore the overall performance
of Victoria’s planning system.
1.3 Recommendations
Measuring the performance of the state’s planning framework
- DPCD should develop a comprehensive strategy with detailed
timelines for the further development and implementation of the performance
measurement framework (Recommendation 4.3).
- DPCD should review and revise the existing performance targets
for the planning scheme amendment process so that they accurately reflect the
elapsed time for decisions to be made on authorisations and approvals (Recommendation
4.4).
Council management of the planning scheme amendment process
Timeliness
Consideration of amendment requests
- Councils should make certain that they perform a comprehensive
initial assessment of the amendment against all the requirements of Section
12 of the Act, and that this is clearly documented in reports to council (Recommendation
5.2).
- standard templates are used for reporting to council
on proposed amendments so that adequate consideration is given to all relevant
matters under Section 12 of the Act
- records of all meetings/discussions with proponents and
DPCD are appropriately documented so that an accurate history of the amendment
is maintained and action items are addressed by all participants (Recommendation
5.3).
Notification
- DPCD, in consultation with councils, should develop a clear
definition of the term ‘materially affected’, including guidelines for making
determinations to facilitate consistency across councils (Recommendation
5.4).
- assessments of who is materially affected have been adequately
undertaken, and appropriately documented
- all parties that have made submissions are appropriately
noted and considered (Recommendation 5.5).
Assessment following exhibition
- DPCD, in consultation with councils, should develop a standard
report template so that the requirements of the Act, issues raised by submitters,
and relevant planning scheme provisions are consistently and comprehensively
discussed in council officer reports when assessing amendments following public
exhibition (Recommendation 5.6).
- DPCD should assist councils to develop and implement procedures
to require targeted, risk-based peer reviews of officer reports against defined
standards before transmission to council, to provide assurance that all relevant
matters have been included and comprehensively addressed, and that evidence
of this is documented (Recommendation 5.7).
Panel hearings
Adoption and submission to minister
- Councils should review their quality assurance arrangements
to put in place appropriate measures whereby requirements arising from the adoption,
submission to, and approval of amendments by the minister are properly addressed
by council and that evidence of this is retained (Recommendation 5.9).
Fees
- Councils should ensure that:
- all relevant staff are made aware
of the fee provisions within the Act and Regulations
- proponents (where relevant) are
clearly identified at the outset, and processes initiated to identify and collect
relevant fees
- effective controls are put in place
for the timely invoicing and payment of relevant fees for key stages in the
amendment process
- appropriate procedures are put
in place to facilitate prompt follow-up of outstanding payments
- records and receipts of all payments
received are accurately maintained on file (Recommendation 5.10).
Council management of the planning permit process
Pre-application meetings
- Councils should review the adequacy of their pre-application
procedures, and establish arrangements for systematically recording and documenting
on file:
- whether a pre-application meeting was conducted in respect
of an individual application
- the details as well as key actions arising from pre-application
meetings with applicants (Recommendation 6.1).
Lodgement
- Councils should ensure
that:
- records for all key events associated with an application
are accurately kept and recorded in the register
- all requests for further information are carried out
in accordance with the requirements of the Act, and that lapse dates are
enforced
- neighbourhood and site descriptions are provided where
required and assessed by council to determine whether they meet the requirements
of the planning scheme
- the register of applications is maintained accurately
in accordance with the requirements of Schedule 2 of the Regulations (Recommendation
6.2).
- Councils should review
and, where necessary, strengthen their quality assurance processes so that::
- applications submitted at lodgement
are accurate and complete
- all documents and plans are appropriately
date-stamped and recorded on file
- thorough preliminary assessments
are conducted, checklists completed, and the outcomes communicated effectively
to planners and recorded on file
- further information requests are
issued promptly, and addressed prior to giving notice (Recommendation
6.3).
Amendments before decision
- Councils should:
- implement targeted training for staff to improve their
understanding of the requirements associated with Sections 50, 50A and 57A
of the Act
- review and, where necessary, revise their quality assurance
processes so that amendments to applications made before decision are reviewed
for compliance with the Act and planning scheme (Recommendation
6.4).
Notification
- to facilitate consistency across councils DPCD, in consultation
with councils, should identify the factors to be taken into account when assessing
material detriment and develop guidelines for making such determinations (Recommendation
6.5).
- assessments of material detriment have been adequately
undertaken, and appropriately documented
- notification decisions are made at the appropriate stage
of the process, and are informed by a properly documented site inspection
- notification decisions comply with the Act and the planning
scheme
- applicants have complied with their obligations (where
relevant) in relation to the placement and maintenance of site notices (Recommendation
6.6).
Referral authorities
- Councils should:
- implement training for staff to improve their understanding
of the planning scheme provisions for referral
- establish appropriate quality assurance procedures to
make certain that applications are referred correctly and that copies of
decisions are always forwarded to relevant referral authorities
- review their internal referral processes and establish
clear policies, procedures and standards to enable them to be carried out
in a timely fashion (Recommendation 6.7).
Assessment
- Councils should review their internal assessment processes
and make certain that staff have adequate knowledge to identify and consider
all the relevant matters under the Act and planning scheme applicable to different
types of applications (Recommendation 6.8).
- When assessing applications, councils should make certain
that proper consideration is documented and given to all relevant:
- matters under Section 60 of the Act
- zone, overlay and other controls
- permit triggers
- state and local policy provisions (Recommendation
6.9).
- Councils should review their quality assurance procedures
to make certain that:
- appropriate report templates, incorporating guidelines
and criteria for assessment, are developed and properly used by planning staff
- oversight mechanisms are appropriate for providing a
reasonable level of assurance that sufficient consideration is given to all
relevant matters under the Act and planning scheme by assessing officers, and
that this is properly documented and transparent to all parties (Recommendation
6.10).
State-wide approach to improving statutory planning in councils
RESPONSE provided by the Secretary, Department of Planning and
Community Development
It is pleasing that a key finding of the report is that the underlying
architecture of Victoria’s planning system is sound. I acknowledge that the Department
of Planning and Community Development has an important role to oversight the operation
and reform of the planning system. The department has initiated a continuing program
of initiatives in this area and strongly supports a continuous improvement approach
to the management of Victoria’s planning system.
The department agrees in-principle with the recommendations in
the report and will work closely with the local government sector and other key
stakeholders to develop an agreed framework for an improved performance measurement
and reporting regime as recommended in the report. The following broad comments
are provided in addition to the detailed response to the recommendations that are
included in parts 4, 5, 6 and 7 of this report.
Measuring the performance of the state’s planning system
The department is progressively developing new systems to address
these issues. In particular, state-wide planning permit activity reporting is now
operational and this is currently being expanded to include reporting on the timeliness
of permit application decision-making and other matters.
Council management of the planning scheme amendment process
The department is currently undertaking an internal review of
the amendment process to identify opportunities to further streamline the process.
This will provide the opportunity to simplify and improve procedures and practices
to ensure efficiency and facilitate compliance with statutory requirements. The
findings of your report will provide valuable input into this review.
Council management of the planning permit process
As you acknowledge, Victoria has maintained a long standing program
of continuous improvement of the planning system. While the local government sector
will be primarily responsible for giving effect to these recommendations, the department
will work co-operatively with the sector to achieve the outcomes sought by the recommendations.
State-wide approach to improve statutory planning in councils
The department will work with the local government sector and
the broader planning industry towards improvement of overall standards in the industry.
It is expected that further implementation of ePlanning in accordance with the ePlanning
Roadmap will assist in this regard and will enable more sophisticated performance
measurement in the future.
As you would be aware the Premier announced a major review of
the Planning and Environment Act 1987 in his annual statement of government intentions
in February. This review will provide further opportunities to streamline and simplify
planning processes and to improve reporting and quality assurance opportunities.
The recommendations included in the report will be an important input into this
review.